Pinnacles Build October 20, 2017
Things have been going off here at Keefer Lake! We are firing on all cylinders to beat the coming snow.
Things have been going off here at Keefer Lake!
We are firing on all cylinders to beat the coming snow.
The roof is done! Next week we will continue putting on the Hardy Board siding and finishing the trim on the exterior windows. The exterior will then be complete!
The inside of the Pinnacles Lodge is looking great. All the framing, electrical and plumbing are done and waiting for inspection. The wood stoves are going in as we speak so we have some heat. Next week we begin the drywall stage and then on to final finishing touches.